HEBRON — A proposed 3-megawatt solar facility off Meeting House Road has cleared the Connecticut Siting Council, but the developer must complete additional permitting and safety requirements before the project can be built and begin operating.

The council issued its ruling November 12, with 20 conditions detailed in a November 16 decision letter. It found that the Hebron Solar One project would not have a substantial adverse environmental effect.

Before construction, the developer must submit its state stormwater permit. A Connecticut-licensed professional engineer must also stamp the final racking-system design before installation. The council requires at least two weeks’ written notice before site construction begins.

Emergency planning is another step before the facility can operate. The final response plan must go to the council and local emergency responders, and the Hebron fire marshal must certify that training is complete and the plan is approved. The decision also requires emergency-contact signs and a bond covering eventual decommissioning.

The council’s staff report describes a construction plan starting in spring 2027 and lasting about seven months. That is a projected schedule, not a report that work has begun. The report estimates about 19 acres of disturbance and 6.8 acres of tree removal.

The council also recommended that the developer and Eversource explore equipment arrangements that would reduce the visibility of the electrical interconnection. Future project changes remain subject to council review.