ASHFORD — Residents can ask the Connecticut Department of Transportation about its plan for the Route 89 crossing over Basset Brook at a virtual meeting Wednesday, December 16, at 6:30 p.m.

The crossing on Westford Road carries two lanes over a metal pipe arch built in 1958, according to a CTDOT project presentation. The department says replacing structural elements would extend the life of the crossing. The proposal involves permanent drainage and slope easements as well as temporary construction easements.

CTDOT estimates construction will cost about $4 million, with federal funds expected to cover 80 percent and the state the rest. Work could begin in spring 2028, depending on funding, rights-of-way acquisition and permits. The November 16 announcement gives no closure or detour dates.

A question-and-answer session will follow the presentation. To listen by phone, call 877-853-5257 and enter meeting ID 884 5845 4473. CTDOT will accept comments through December 30 at DOTProject0003-0113@ct.gov or 860-594-2020. Include project number 0003-0113.